Migrating a governance process from V8.0.0
The governance process was redesigned for IBM® Business Process Manager V8.0.1. As a result, governance processes that were developed in V8.0.0 cannot be reused; they must be revised to fit the V8.0.1 design.
About this task
In IBM Business Process Manager V8.0.0, you cannot configure governance to use a specific governance process snapshot. Instead, in V8.0.0, Process Center always runs the configured governance process from the tip version. In versions later than V8.0.0, you can configure governance with a specific governance process snapshot. This redesign has been accompanied by a number of other modifications. As a result, governance processes developed in IBM BPM V8.0.0 cannot be migrated automatically to newer versions of IBM BPM.
- In V8.0.0, only two governance processes ran in the Process Center, one for installation and one for snapshot status. In V8.0.1 and later, you can have many governance processes.
- In V8.0.0, governance was applied to one process application or toolkit at a time. In V8.0.1 and later, governance is always running and there is a system-wide default process in the System Governance toolkit. However, you can still configure a custom governance process for one process application or toolkit at a time.
- In V8.0.0, there were services in the System Governance toolkit that the governance processes used. In V8.0.1 and later, many of those services are still used, with the same interface as they had in V8.0.0.
- The GOV prefix was used on business object names in V8.0.0. The prefix is no longer used in V8.0.1.
- In V8.0.0, a governance process was started by a message start event bound to an undercover agent (UCA). In V8.0.1 and later, no UCA is used; an associated governance process instance is started directly.
- In V8.0.0, a governance process was constructed just like any other business process definition (BPD). In V8.0.1 and later, the governance process developer must use one of two governance templates to create the BPD.
Because of these design changes, you must make a number of manual changes to a V8.0.0 governance process before you can use it in later versions of IBM BPM. You cannot migrate a process instance.
Procedure
To migrate governance process from V8.0.0, complete the following steps: