A management of change (MOC) request is used to formally
propose an engineering or operational change. You create management
of change (MOC) request records to initiate changes to assets, locations,
configuration items, or items.
Procedure
- In the MOC Requests application, click the New
MOC Request icon.
- Complete all the essential fields (*) and the remaining fields, as needed. Typically, you
must complete the following fields on the main tab of the application.
| Field |
Description |
| Priority |
If you plan to schedule the work, specify a priority for the change. |
| Location, Asset, Configuration Item, or Item |
You can create the management of change record for a location, an asset, a configuration
item, or for an item. |
| Operating Policy and Operating Procedure |
Specify the operating policy that is associated with the management of change request
record. You can also specify an operating procedure. The operating policy and the operating
procedure must be in Active status. |
| MOC Type |
Specify the type of management of change request, such as deferral or MOC, and if the
change is temporary or high risk. |
| Multi Assets, Locations, and CIs |
Specify the primary affected asset, location, and configuration item in the designated
fields. Then, you can specify multiple related assets, locations, and configuration items in the
Multi Assets, Locations, and CIs window. For example, a service bulletin that
requires engineering approval to implement might apply to the same type of valve that is used in
multiple locations. You might create a management of change request record, linked to each location
that uses the valve, to manage the change for all of the valves. |
- Save the record.
- Optional: Use the additional tabs in the MOC Requests application to add or
modify information for this record. Save the record.
For example, to specify the work
orders or the tickets that are associated with this request, use the Related