Closing a service call by using IBM® PowerKVM

Perform the following steps to prepare the server to return to the customer.

Consider the following prerequisites before performing the procedure:
  • Return the server to the state that the customer normally uses, such as IPL type, IPL mode, and the way the system is configured or partitioned.
  • Ensure that server verification has been performed and that no problems require additional service actions.
  1. Do you have any field-replaceable units (FRUs) (for example, cards, adapters, cables, or devices) that were removed during problem analysis that you want to replace in the system?
    • Yes: Reinstall all of the FRUs that were removed during problem analysis. Continue with the next step.
    • No: Continue with the next step.
  2. Have you already performed Verifying a repair?
    • Yes: Continue with the next step.
    • No: Perform Verifying a repair. Then continue with the next step.
  3. The system hardware is functioning correctly.

    If the check log LED is still on, turn off the LED as described in Activating and deactivating LEDs.