Completing the server setup

Learn more about the tasks you must perform to complete your managed system installation.

If you have an Hardware Management Console (HMC), use it to complete the following high-level tasks:
  1. Update the time of day on the managed system by using the Advanced System Management Interface (ASMI).
  2. Check the firmware level on the managed system.
  3. If required, update the managed system firmware levels.
  4. Confirm that the system is in standby mode. The green power status indicator on the front control panel is flashing slowly, and the dc out indicator lights on the power supplies are flashing. If none of the indicators are flashing, check the power cord connections.
  5. Power on the managed system.
  6. Create logical partitions (or virtual servers), or deploy an imported system plan.
  7. Install an operating system, if it is not already installed.

For instructions, see Completing the server setup by using a Hardware Management Console.

If you do not have an HMC, complete the following tasks:

  1. Check the firmware level on the managed system and update the time of day using ASMI.
  2. Confirm that the system is in standby mode. The green power status indicator on the front control panel is flashing slowly, and the dc out indicator lights on the power supplies are flashing. If none of the indicators are flashing, check the power cord connections.
  3. Power on the managed system.
  4. Install and update an operating system, if it is not already installed.
  5. Update the system firmware, if required.

For instructions, see Completing the server setup without using a management console.