Changes to the timing of an escalation at run time
Sometimes a business situation requires that you change
the timing of an escalation that was specified when the escalation
was defined. The escalation state determines which of these times
you can change, and when these actions can be taken. You can use the update method
of the Human Task Manager API to modify the appropriate escalation
property. You can also use the Tasks List widget or the Escalations
List widget in Business Space to override the scheduled escalation
time, and start an escalation immediately.
You can change the timing of the initial escalation and when the
escalation repeats in one of the following ways:
- Using a specific time
- Using a duration, for example, 2 days, based on a calendar, such
as a business calendar. You can also use the following constants in
duration expressions:
- DURATION_INFINITE
- The initial escalation or the repeated escalations are canceled.
Initial escalation
You can use the escalationTime and the durationUntilEscalated properties to change the timing of an escalation. The escalation state determines which of these properties you can use.
- Inactive state
- In this state, you can override the duration until escalated value that was defined for the escalation by setting the durationUntilEscalated property to a valid value for the calendar that is used by the task. To prevent the escalation from starting, set the durationUntilEscalated property to DURATION_INFINITE.
- Waiting state
- In this state, you can reschedule the initial escalation or cancel
it. You can reschedule the escalation by setting either the escalationTime
property or the durationUntilEscalated property to a valid value for
the calendar that is used by the task. To cancel the escalation, set
the durationUntilEscalated property to DURATION_INFINITE.
You can also trigger the escalation manually using the Human Task Manager API triggerEscalation method.
Repeated escalations
If the task is in the
escalated state and the expected task state has not yet been reached,
you can use the escalationTime and the durationUntilRepeated property
to change the timing of repeated escalations depending on the escalation
state.
- Inactive and waiting state
- In this state, you can override the duration until repeated value that was defined for the escalation by setting the durationUntilRepeated property to a valid value for the calendar that is used by the task. To prevent the escalation from repeating, set the durationUntilRepeated property to DURATION_INFINITE.
- Escalated state
- In this state, you can reschedule the repetition of the escalation or cancel it. You can reschedule the repetition of the escalation by setting either the escalationTime property or the durationUntilRepeated property to a valid value for the calendar that is used by the task. To cancel the repetition, set the durationUntilRepeated property to DURATION_INFINITE.