Replacing the power switch and cable in the 8335-GTC system

To replace a power switch and cable, complete the steps in this procedure.

Procedure

  1. Ensure that you have the electrostatic discharge (ESD) wrist strap on and that the ESD clip is plugged into a ground jack or connected to an unpainted metal surface. If not, do so now.
  2. Find the replacement power switch and cable and remove it from the protective plastic envelope.
  3. Insert the power switch and cable into the system as shown in Figure 1. Be careful to route the cable through to the system backplane.
    Figure 1. Replacing the power switch and cable into the system backplane
    Replacing the power switch and cable into the system backplane
  4. Replace the top and side screws for the power switch as shown in Figure 2.
    Figure 2. Replace the top and side screws
    Replace the top and side screws
  5. Using the labels, plug the power switch and cable (A) to the system backplane as shown in Figure 3.
    Ensure that the cable latch clip snaps into place on the connectors.
    Figure 3. Plugging in the power switch and cable
    Plugging in the power switch and cable
  6. Replace the rack installation support on the side of the system as shown in Figure 4.
    Figure 4. Replacing the rack installation support
    Replacing the rack installation support
  7. Secure the cable in the retaining clip on the inside wall of the system.
  8. Replace the disk drive and fan card.

What to do next

Prepare the system for operation. For instructions, see Preparing the 8335-GTC, 8335-GTG, 8335-GTH, 8335-GTW, or 8335-GTX system for operation after you remove and replace internal parts.