Pinned topic Transistion Costs in Objective

‏2013-07-30T09:52:31Z |

Hi

I have a sequencing problem where I have to minimize the transition / change over costs between products and maintain the transition time between them as well. Although I'm able to generate sequences using the changeover time transition matrix in the noOverlap function , I'm not able to define the objective function. Can someone suggest a way for this?

 

 

  • aravindnambiar
    aravindnambiar
    2 Posts
    ACCEPTED ANSWER

    Re: Transistion Costs in Objective

    ‏2013-07-31T17:03:36Z  in response to aravindnambiar

    I managed to solve it. I used typeOfNext in my objective function for the change over cost & used the noOverlap function in the constraint to take care of the change over time.