Pinned topic GanttChart for ClearQuest - project management plugin

‏2013-12-15T01:35:57Z |

GanttChart for ClearQuest is a unique plug-in for IBM Rational ClearQuest developed by CM-Consult. It allows project managers, executives, and all team members to view tasks from the project plan. Project managers like GanttChart because it is easy to use. With two clicks GanttChart allows re-planning tasks, and automatically updates the corresponding task fields. That is GanttChart for ClearQuest allows you to plan tasks directly from ClearQuest in real time mode.

Also, project managers will definitely like the ability to visualize the transition tree of each request. This function not only displays the graphic representation of a state chart, but also allows viewing the number of transitions between states (number of loops). If a task was sent for rework several times, this information will be available in the state chart.

The most important features:

  • Ability to plan and re-plan on the spot, including altering the dates for multiple tasks.
  • Support for user databases with large number of tasks without performance degradation.
  • Convenient display of tasks: color coding of tasks depending in their status (late, completed, not implemented, etc.).
  • Ability to view the user's load for the whole pool of change requests (tasks, defects, requests, etc.).
  • Representation of hierarchy and relations between change requests as aggregate tasks and implementation sequence - complete visualization of relations (hierarchy and relations between tasks).
  • Display of brief information about a task as a tool tip.
  • Display of UML state chart for every task (through the context menu).
  • Ability to open change request forms directly from a chart.
  • Different representations of a project (as a Gantt chart or as resources load by day).

Donload free 60-day full-functional version.

 

Selecting groups of tasks and performing aggregate modifications of planned dates (prolongation, changing execution dates)


 

 

 

 

 

 

 

 

 

 

 

 

 

Selecting groups of tasks and performing aggregate modifications
of planned dates (prolongation, changing execution dates)
  • Haeussler
    Haeussler
    19 Posts

    Re: GanttChart for ClearQuest - project management plugin

    ‏2013-12-16T08:47:00Z  

    Hello Alex,

    they have a version for the CQ Web-Client?

    Thanks and best regards,

    Chris

  • alex-golder
    alex-golder
    12 Posts

    Ответ: Re: GanttChart for ClearQuest - project management plugin

    ‏2013-12-16T10:16:28Z  
    • Haeussler
    • ‏2013-12-16T08:47:00Z

    Hello Alex,

    they have a version for the CQ Web-Client?

    Thanks and best regards,

    Chris

    Hello Chris,

    we plan it to make in version 1.5.  In the current version we support only Eclipse CQ client.

    This release is planned on April, 2014