Pinned topic question about setting Cplex solving MIP problem

‏2012-12-27T21:21:02Z |
I have a very big problem that I would like to use MIP to solve. I do not expect the Cplex would output an optimal solution in time. If I only want to have a best feasible solution found within a given time window, which parameters should I set for Cplex?

Thanks!
Updated on 2012-12-29T20:45:55Z at 2012-12-29T20:45:55Z by SystemAdmin
  • SystemAdmin
    SystemAdmin
    7929 Posts
    ACCEPTED ANSWER

    Re: question about setting Cplex solving MIP problem

    ‏2012-12-28T21:10:26Z  in response to SystemAdmin
    The TiLim parameter is used to stop CPLEX after a specified elapsed time.