Pinned topic Noob - How do I skip tonight's backup?

‏2012-06-22T17:44:06Z |
I am installing an application update tonight that could possibly take several hours (I think there are DB scripts altering a few million records). I want to skip tonight's full system save to allow this process time to complete. if I do a GO BRMSCD option 1 that takes me to "Work with BRM Job Schedule Entries". Once here I just put a HOLD on the appropriate job, correct?
Updated on 2012-06-26T13:00:32Z at 2012-06-26T13:00:32Z by KentKroft
  • SystemAdmin
    SystemAdmin
    353 Posts
    ACCEPTED ANSWER

    Re: Noob - How do I skip tonight's backup?

    ‏2012-06-22T18:42:27Z  in response to KentKroft
    Hi Kent, correct. I would also suggest you do a WRKJOBSCDE and check that you have no other jobs that may have being scheduled that run backups via CL programs

    Thanks
    Mervyn
    • KentKroft
      KentKroft
      2 Posts
      ACCEPTED ANSWER

      Re: Noob - How do I skip tonight's backup?

      ‏2012-06-26T13:00:32Z  in response to SystemAdmin
      Thanks Mervyn. Worked like a charm.