Pinned topic Pack SAP 5.0.1 Idoc Load stage Performance

‏2004-06-04T12:06:38Z |
Hi, we have the Pack for SAP 5.0.1 over DS 6.01r4 and a lot of jobs that sends Idocs to SAP by the Idoc Load Stage. We have a performance problem, when the idocs are sent to Sap, they have a delay of 10 to 15 seconds to arrive to SAP R3.
We clear the SAP's tables where the idocs are storing when they arrive.
How can i put a trace in DS to detect the exact time when the idoc is sending?
Thanks.

Ariel
Updated on 2005-02-02T14:45:20Z at 2005-02-02T14:45:20Z by SystemAdmin
  • SystemAdmin
    SystemAdmin
    160 Posts
    ACCEPTED ANSWER

    Re: Pack SAP 5.0.1 Idoc Load stage Performance

    ‏2004-06-04T15:16:10Z  in response to SystemAdmin
    I don't know of any way to do it directly within DataStage. Your best bet would be to turn on RFC tracing - set the environment variable RFC_TRACE to 1, set the environment variable RFC_TRACE_DIR to a directory path where you know you'll find the trace files, and go from there.
  • SystemAdmin
    SystemAdmin
    160 Posts
    ACCEPTED ANSWER

    Re: Pack SAP 5.0.1 Idoc Load stage Performance

    ‏2005-02-02T14:45:20Z  in response to SystemAdmin
    Is the RFC trace capability mentioned on the DS side or the SAP side?