Pinned topic About Streams' High Availability

‏2013-07-02T03:30:09Z |

Hi,

     Recently think about the Streams' High Availability, as the six manage services can be distributed on several nodes, assume that one node is failed, even the hardware is unavailable, then we can dynamically  add a new server to the GPFS cluster.  

      Then, Can the new server  dynamically add to the streams instance and how to set the failed manage service running on this new adding node?

       Or, can the failed manage service be transferred to another existing active node?  How to do it ? 

Thanks!

  • sbjerry
    sbjerry
    2 Posts

    Re: About Streams' High Availability

    ‏2013-07-02T05:05:51Z  

    I've found the answer in information center, thanks!

    Failed manage services can be manually moved to other active node