Pinned topic Change Schedule Date Time without deleting and resubmitting process

‏2013-08-22T18:41:57Z |

I have run into a situation where we have a process sitting in the Process Monitor with a WA status and WAIT queue.  We had a process which was scheduled to run daily at a specific time.. But one day the connect:direct service wasn't running when the scheduled time elapsed, so now the process is stuck in process monitor with a waiting status with the scheduled date time in the past.  Is there any way that I can modify a processes scheduled execution time, short of deleting and resubmitting the process entirely?

Thanks in advance

  • VolkerFriedrich
    VolkerFriedrich
    156 Posts
    ACCEPTED ANSWER

    Re: Change Schedule Date Time without deleting and resubmitting process

    ‏2013-08-30T15:53:16Z  in response to mshagena

    Did you try to hold the process first and then release it again? Maybe restarting Connect:Direct one more time may help?

    Normally it should not be an issue that Connect:Direct was down at the scheduled time. As soon as it starts up again, it should run any past processes automatically and advanced the new scheduled time.