Organization|Project switcher by default allows switching to a Capital project.

Is it possible to switch to Facility Project?

  • scott_ruch_wipro
    scott_ruch_wipro
    13 Posts
    ACCEPTED ANSWER

    Re: Switch to Facility Project scope

    ‏2017-11-01T16:27:50Z  

    Kirill,

    No. Facility Project was not created with the same structure as Capital Project and the silo behavior that is associated to Capital Project is not provided for Facility Project. It would be possible to create a custom solution to do so, or if you would like to see this sort of behavior in the as-shipped application, you might enter an RFE to request that behavior.

  • scott_ruch_wipro
    scott_ruch_wipro
    13 Posts

    Re: Switch to Facility Project scope

    ‏2017-11-01T16:27:50Z  

    Kirill,

    No. Facility Project was not created with the same structure as Capital Project and the silo behavior that is associated to Capital Project is not provided for Facility Project. It would be possible to create a custom solution to do so, or if you would like to see this sort of behavior in the as-shipped application, you might enter an RFE to request that behavior.