Question & Answer
Question
When receiving a PO in the receipts application if you change the date in the "Actual Date" field to a date in the past. The exchange rate used is not the rate for that date.
Cause
This is working as designed.
Answer
The exchange rate used upon receipt is the rate as at the date of the Approval of the PO and cannot be changed.
[{"Product":{"code":"SSLKT6","label":"IBM Maximo Asset Management"},"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Component":"Exchange Rates","Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"7.5","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]
Was this topic helpful?
Document Information
Modified date:
17 June 2018
UID