Error description

  • Automatic Geometry not spacing the ICOMs in the OV-05 Activity
    Model diagram in System Architect
    
    Workaround:
    
    Just save the diagram after changing the Vertical and Horizontal
    ICOM Spacing
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    This problem came to light because of an anomaly in the
    user's encyclopedia. The visual diagram shows 5 Function Box
    nodes arranged nicely from top-left down to bottom-right.
    However, internally, they are not stored in the encyclopedia
    in that order, and so re-spacing of ICOM lines takes place
    in an arbitrary order.
    

Problem conclusion

  • Automatic Geometry is actually done in three steps. Steps 1
    and 2 work OK and, left by themselves, would result in a
    suitably redone diagram. Step-3 also works OK, but only if
    Function Box nodes are processed in the correct order
    (top-left down to bottom-right). When done out of order,
    Step-3 can mess up the good work done by Step-1 and Step-2.
    
    Respacing ICOM lines can require making Function Box symbols
    bigger and then shifted to make room for each other. This
    fix does a better job of routing ICOM lines after the
    symbols have been resized and shifted.
    

Temporary fix

Comments

APAR Information

  • APAR number

    PM65103

  • Reported component name

    TLOGIC SYS ARCH

  • Reported component ID

    5724V68SA

  • Reported release

    B41

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt

  • Submitted date

    2012-05-21

  • Closed date

    2012-12-21

  • Last modified date

    2012-12-21

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    TLOGIC SYS ARCH

  • Fixed component ID

    5724V68SA

Applicable component levels

  • RB41 PSN

       UP

[{"Business Unit":{"code":"BU053","label":"Cloud & Data Platform"},"Product":{"code":"SS6RBX","label":"Rational System Architect"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"11.4.1","Edition":"","Line of Business":{"code":"LOB45","label":"Automation"}}]

Document Information

Modified date:
21 December 2012