  • Closed as program error.

Error description

  • Tested with Linux and Synergy 7.1.0.5
    
    1) Start a Synergy session in Web mode.
    In Synergy:
    Create a new task
    Create a new project (workarea in linked mode)
    Create a subdirectory called 'subdir' for example in this new
    project
    
    2) In a terminal go in the project's workarea.
    ##
    ls -al
    total 16
    drwxr-xr-x 3 gperrin users 4096 Feb  3 10:17 .
    drwxr-xr-x 3 gperrin users 4096 Feb  3 10:15 ..
    -r--r--r-- 1 gperrin users   54 Feb  3 10:15 .ccmwaid.inf
    drwxr-xr-x 2 gperrin users 4096 Feb  3 10:17 subdir
    ##
    
    Create manually, in the terminal, a link pointing to the new sub
    directory 'subdir':
    ln -sf subdir linkme
    ##
    ll
    total 16
    drwxr-xr-x 3 gperrin users 4096 Feb  3 10:18 .
    drwxr-xr-x 3 gperrin users 4096 Feb  3 10:15 ..
    -r--r--r-- 1 gperrin users   54 Feb  3 10:15 .ccmwaid.inf
    lrwxrwxrwx 1 gperrin users    6 Feb  3 10:18 linkme -? subdir
    drwxr-xr-x 2 gperrin users 4096 Feb  3 10:17 subdir
    ##
    
    3) In Synergy, run a Sync Workarea on the project.
    The link is detected and the new conflict is reported in
    Synergy.
    Right click on the object in the Conflict dialog, and select
    'Keep Workarea changes'
    
    =? The object 'linkme' is created in Synergy. With the correct
    type 'symlink'.
    =? But the link is deleted in the workarea
    ##
    ll
    total 16
    drwxr-xr-x 3 gperrin users 4096 Feb  3 10:20 .
    drwxr-xr-x 3 gperrin users 4096 Feb  3 10:15 ..
    -r--r--r-- 1 gperrin users   54 Feb  3 10:15 .ccmwaid.inf
    drwxr-xr-x 2 gperrin users 4096 Feb  3 10:17 subdir
    ##
    
    
    4) Run a Sync workarea on the project again:
    A new conflict 'File removed from the workarea' is detected for
    the object 'linkme'.
    -Select the option 'Discard Workarea changes'
    =? The symlink object in Synergy is kept.
    =? But the link is still not created in the workarea.
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    Link in the workarea, for symlink object, deleted by the
    Sync Workarea
    

Problem conclusion

  • Fixed in Synergy 7.2.0.2 and planned to be fixed in Synergy
    7.1.0.6.
    

Temporary fix

Comments

APAR Information

  • APAR number

    PM57460

  • Reported component name

    TLOGIC SYNERGY

  • Reported component ID

    5724V66SN

  • Reported release

    710

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt

  • Submitted date

    2012-02-06

  • Closed date

    2012-03-20

  • Last modified date

    2012-03-20

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    TLOGIC SYNERGY

  • Fixed component ID

    5724V66SN

Applicable component levels

  • R710 PSN

       UP

[{"Business Unit":{"code":"BU053","label":"Cloud & Data Platform"},"Product":{"code":"SSC6Q5","label":"Rational Synergy"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"7.1","Edition":"","Line of Business":{"code":"LOB45","label":"Automation"}}]

Document Information

Modified date:
20 March 2012