Error description

  • The deploy operation for Z Development and Test Environment
    Enterprise Edition (ZD&T EE) 12.0.5  relies on being able to SSH
    to the target z/OS to determine when the IPL is complete.  It is
    also used as a means of being able to initiate data set restore
    post IPL.  If SSHD is not started with the IPL process then the
    tooling will time-out after 10 minutes as a successful SSH
    connection to the target z/OS is never established, even though
    the IPL can be completed successfully.  As a result the tooling
    thinks the IPL failed and will show the deploy operation as
    failed.  The requirement for SSHD to be running in order to show
    a deploy to appear successful needs to be clearly indicated in
    the documentation.
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * ZD&T Tools users.                                            *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * The deploy operation relies on being able to SSH to the      *
    * target z/OS to determine when the IPL is complete.  It is    *
    * also used as a means of being able to initiate data set      *
    * restore post IPL.  If SSHD is not started with the IPL       *
    * process then the tooling will time-out after 10 minutes as a *
    * successful SSH connection to the target z/OS is never        *
    * established, even though the IPL can be completed            *
    * successfully.  As a result the tooling                       *
    * thinks the IPL failed and will show the deploy operation as  *
    * failed.                                                      *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    The requirement for SSHD to be running in order to show a deploy
    to appear successful needs to be clearly indicated in the
    documentation.
    

Problem conclusion

  • The following documentation has been added:
    To ensure that a deployment is shown as success after IPL is
    complete, SSHD must be running. The deployment operation for
    ZD&T Enterprise Edition relies on being able to SSH to the
    target z/OS to determine when the IPL is complete. It is also
    used as a means of being able to initiate data set restorage
    after IPL. If SSHD is not started with the IPL process, the
    Enterprise Edition web server will time out after ten minutes
    because a successful SSH connection to the target z/OS is not
    established. Even the IPL can be completed successfully, the web
    server determines that the IPL fails, and shows that the
    deployment operation fails.
    
    This is now available as part of IBM Z Development and Test
    Environment 13.0.
    Product web page:
    https://www.ibm.com/us-en/marketplace/z-systems-development-test
    -environment
    Fix List:
    https://www-01.ibm.com/support/docview.wss?uid=swg27044017
    

Temporary fix

Comments

APAR Information

  • APAR number

    PH27351

  • Reported component name

    ZSYS DEV AND TE

  • Reported component ID

    5725G3900

  • Reported release

    C00

  • Status

    CLOSED DOC

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2020-07-10

  • Closed date

    2020-12-09

  • Last modified date

    2020-12-09

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

Applicable component levels

[{"Line of Business":{"code":"LOB35","label":"Mainframe SW"},"Business Unit":{"code":"BU054","label":"Systems w\/TPS"},"Product":{"code":"SSTQBD","label":"Rational Development and Test Environment for z Systems"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"C00"}]

Document Information

Modified date:
10 December 2020