Error description

  • The connection factories set for the Process Server and
    Performance Data Warehouse function have specific endpoints and
    transport chain specified to support secured communication with
    the buses by the Process Designer.  The provider endpoint value
    included information for non secured access as well which is not
    valid.  Also when a cluster was extended that supported the
    messaging engines for these connection factories, the new
    cluster member endpoint information was not added to the
    provider endpoint information.  This fix removes the unsecured
    transport chain information and will correctly update the
    endpoint information when a cluster is extended.
    

Local fix

  • manual config
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:  IBM Business Process Manager v7.5.1 users   *
    *                  who have a Network Deployment               *
    *                  configuration.                              *
    ****************************************************************
    * PROBLEM DESCRIPTION: When a cluster member with              *
    *                      messaging engines, the inbound          *
    *                      provider endpoint value is not          *
    *                      updated with the correct ports.         *
    ****************************************************************
    * RECOMMENDATION:  Apply with JR42121.                         *
    ****************************************************************
    
    The connection factories set for the Process Server and
    Performance Data Warehouse function have specific endpoints and
    transport chain specified to support secured communication with
    the buses by the Process Designer.  The provider endpoint value
    included information for non secured access as well which is
    not
    valid.  Also when a cluster was extended that supported the
    messaging engines for these connection factories, the new
    cluster member endpoint informa
    

Problem conclusion

  • This fix removes the unsecured
    transport chain information and will correctly update the
    endpoint information when a cluster is extended.
    
    The interim fix is available on fix central and also in future
    releases.
    

Temporary fix

Comments

APAR Information

  • APAR number

    JR42442

  • Reported component name

    BPM ADVANCED

  • Reported component ID

    5725C9400

  • Reported release

    751

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt

  • Submitted date

    2012-04-04

  • Closed date

    2012-07-10

  • Last modified date

    2012-07-10

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    BPM ADVANCED

  • Fixed component ID

    5725C9400

Applicable component levels

  • R750 PSY

       UP

[{"Business Unit":{"code":"BU053","label":"Cloud & Data Platform"},"Product":{"code":"SSFTN5","label":"IBM Business Process Manager Advanced"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"7.5.1","Line of Business":{"code":"LOB45","label":"Automation"}}]

Document Information

Modified date:
12 October 2021