IV94520: THE LABOR AND AMCREW DATA SOURCE UNDER ADDITIONAL RESOURCES WILL NOT SHOW VALUES IN GRAPHICAL ASSIGNMENT.

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as program error.

Error description

  • The following issue was reproduced in Maximo 763.
    
    Steps to reproduce the issue:
    
    1. Create a work order, add location, add a target start date,
    duration as well.
    
    2. Move to the plans tab and plan for 2 labor, carp and elect,
    save the work order.
    
    3. Create a new scheduler record, add schedule, calendar =day,
    shift =day, remove check marks from the restrict work to dates,
    rolling project and preserve schedule start dates.
    
    4. In the query section add the work order number created
    earlier. Save.
    
    5. Move the Graphical Assignment application, under more action
    use the create work list from schedule option, chose the
    schedule we created earlier, save.
    
    6. Move to the assignment view tab, here we will see the craft
    we planned for, as well as any labor record that has the crafts
    listed as well.
    
    7. Move back the work list tab, let's add a new row under the
    additional resources section. Let's add 2 data sources, AMCREW
    and labor, add the values needed for both. Save.
    
    Move the assignment view tab and notice that you will not see
    entries there for what was just added. The current code is not
    coded to work against the Labor or AMCREW, the fix will be to
    remove the 2 entries from the list.
    

Local fix

  • N/A
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * maximo scheduler                                             *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * THE LABOR AND AMCREW DATA SOURCE UNDER ADDITIONAL RESOURCES  *
    ****************************************************************
    * RECOMMENDATION:                                              *
    * Apply fixpack  Release 7.6.0.8 of Base Services or request   *
    * an interim fix                                               *
    ****************************************************************
    

Problem conclusion

  • Fix has been made to fix....The fix for this APAR is contained
    in the following maintenance package:
    		 | release\fix pack\interim fix for  Release 7.6.0.8 of Base
    Services
    

Temporary fix

Comments

APAR Information

  • APAR number

    IV94520

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    763

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2017-03-23

  • Closed date

    2017-03-27

  • Last modified date

    2017-03-27

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

  • R763 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"763","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
27 March 2017