Hi,
     Our development and integration team uses UCM.

     One of the situation requires baseline to be dynamic for a project.

        Base line of Project B is LATEST ( successfully built and tested ) of
        Project A.
        The baseline of Project B is dynamic.

     I could think of copying the code to a directory ( first A then B ) and
     then work (build ) on that.

     But that would involve tracking the elements and their source.

     I would like to do this in possible best way.

     I would like to know if some one has faced similar situation.

     Would appreciate if you could share your thoughts and views on the subject.

Thanks