RE: [cciug] Rebase problem

From: Alla Okun (alla_okun@creoscitex.com)
Date: Thu Sep 21 2000 - 05:03:42 EDT


Thanks for your suggestion. I really did tried it already
and what I got is the error that "Rebase is not complete"
so I could not reset the activity. The good new is that I found
another way to solve this problem just now - I used the command
line option of Rebase ( cleartool> rebase - complete).
This did worked without any problem !!! The funny thing is that
when I came back to GUI and tried to Complete Rebase it still
gave me the same error "Unable to reset the rebase activity" ...
Seems like a real "big" bug !!

Thanks again

Alla Okun
Software Infrastructures
PWSD - CreoScitex Israel
Tel: 972-9-9597854
Fax: 972-9-9597666

> -----Original Message-----
> From: Melody Haines [SMTP:melody_haines@mindspring.com
> Sent: Thu 21 September 2000 3:19
> To: Alla Okun
> Subject: Re: [cciug] Rebase problem
>
>
>
> Just something to try if you didn't figure this out already, right click
> on
> your dev view and set the default activity to something else but rebase.
> This might allow the rebase activity to reset to the default activity
> after
> the operation is complete. Just a thought.
>
> At 10:22 AM 9/19/00 +0200, you wrote:
> >
> >Did somebody encountered the following problem during REBASE
> >of the development stream:
> >
> >At the end of the "Complete" stage of Rebase I got the following error:
> >
> >Unable to unset integration activity "rebase xxxx" in view "my_view"
> >When I press OK the second message appears :
> >
> >Setwork operation failed in view. More information might be available in
> >view_log on host: .....
> >Could not determine stream for view
> >Unable to unset integration activity
> "rebase.xxxxxx_06586.20000914.164650"
> >in view "my_view".
> >Unable to undo set of integration activity.
> >
> >I looked at the logs - no related messages.
> >
> >When I press Close the same message appears again and then Rebase
> finishes
> >with the message:
> >
> >"The rebase operation was not completed successfully"
> >
> >Note that all files are checked in but when I try to work with the view
> >(checkout)
> >the message appears saying :
> >
> >View "my_view" is set activity to activity
> >"rebase.xxxxxx_06586.20000914.164650" which is currently
> >involved in an active rebase operation. The set activity of this view may
> >not be changed until the opearion
> >has completed.
> >
> >If I try to reset activity using CC explorer I got the same message !
> >
> >Deadlock ??!!
> >
> >Any ideas ???
> >
> >Alla Okun
> >Software Infrastructures
> >PWSD - CreoScitex Israel
> >Tel: 972-9-9597854
> >Fax: 972-9-9597666
> >
> > - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
> >
> >
> >
> > http://clearcase.rational.com/cciug/mailing_list.html
> >
 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -



This archive was generated by hypermail 2b29 : Sun May 06 2001 - 00:26:43 EDT